Project Description

Perth Domestic Airport

Perth Domestic Airport

Working with ISIS/Shape

We have completed a full upgrade to QANTAS terminal internal and external.

Challenge

To erect scaffolds for refurbishment of sections of first floor which is at its full load capacity.

Solution

Engineered cantilevered scaffolds built out of hours for minimal disruption.

Time: 6-8 weeks

Result

Delivered with zero incidents on time and on budget.

Client Feedback

“I have completed numerous difficult scaffold installations on my projects with the help of JB Scaffolding. I’ve found them easy to deal with, WHS conscious, effective problem solvers, and fairly priced in their field. I would not hesitate in recommending JB Scaffolding to others.”
Nicholas Mills, Project Engineer, Shape, Perth WA